Scope of Work
- Completed initial consultations and on-site assessments
- Developed concept designs and secured concept approval
- Obtained DHA initial approval
- Prepared full detailed drawings for execution
- Secured all required government authority approvals
- Executed complete fit-out works to approved specifications
- Achieved DHA final approval and Building Clearance Certificate
Key Highlights
- End-to-end delivery from concept through final certification
- Coordinated multi-authority submissions for accelerated approval cycles
- Detailed drawings aligned with health, life safety, and fit-out standards
- Zero non-conformities at final inspection and smooth handover
Challenges & Solutions
- Multi-authority alignment: Mapped requirements into a tracked submission matrix to prevent rework.
- Program certainty: Locked long-lead finishes early and sequenced trades for continuous site progress.
- Compliance assurance: Ran internal QC against DHA and local code checklists prior to inspections.
Services Provided
Concept Design • Detailed Design • Authority Approvals • DHA Approvals • Fit-Out Execution • Handover Documentation